Synergy’s boss Fip Motilall is still being held to the September 9 deadline for the completion of the Amaila Falls access road project, government’s technical advisor Walter Willis says.
The government has not modified any part of the US$15.4 million project, Willis disclosed even as Synergy is badly behind schedule. According to Willis, Synergy is still expected to produce an all-weather road to the site, as well as the Butakari pontoon crossing, the Kuribrong bridge and 15 timber bridges.
Synergy won the contract for “the upgrading of approximately 85 km of existing roadway, the design and construction of approximately 110 km of virgin roadway, the design and construction of two new pontoon crossings at