Construction of the new One Mile Primary School building is progressing satisfactorily, according to a supervisor on the 18-month project.
Work started in February and in spite of some interruptions due to periods of heavy rainfall, construction has progressed ahead of schedule.
It is anticipated that laying of blocks, casting and the roof will be completed within the next two months. Payroll Clerk on the project, Alieshaw Barker, said 33 persons are employed on the project including labourers, skilled and semi-skilled workers.
Government has allocated $171 million for the construction of a new One Mile Primary School building