Edghill asks Auditor General to probe East Bank overpass project

The pedestrian overpass above the Diamond Public Road
The pedestrian overpass above the Diamond Public Road

Minister of Public Works Juan Edghill has asked Auditor General Deodat Sharma to conduct a forensic audit into the construction of the overhead pedestrian crossings along the East Bank of Demerara which were built under the former APNU+AFC administration.

In a letter to Sharma released yesterday, Edghill cited the need for the forensic audit to be conducted since according to him the Government did not get “value for money” for the installation and operation of the elevators.

Although the elevators were part of the project, he said they are still incomplete after more than two years.

The project was funded by the Inter-American Development Bank (IDB).

Contracts were awarded to two companies for the construction of five overhead walkways.

S.Jagmohan Hardware Supplies and Construction Services was  awarded a total of US$728,973 to construct crossings at Providence and Diamond while a contract of $1,034,326 was awarded to B&J Civil Works to build crossings at three locations namely: Eccles, Houston and Peters Hall.

These contracts were executed on April 27, 2017.  Later, with approval from the National Procurement and Tender Administration Board (NPTAB) and the IDB, the contracts were amended and the period for completion extended to September 30, 2018.

Former Minister of Public Infrastructure David Patterson, in May 2017 had announced government’s plan to construct the crossings, which were expected to significantly reduce accidents, save on time for those travelling from Diamond and enable a free flow of traffic.

In addition, Edghill noted that under the former Ministry five complete solar voltaic systems were procured and installed at the five crossings.

Farfan and Mendes Limited were given the contract which was effective from July 8, 2018 to supply, install and maintain the solar voltaic systems for a ten-year period at a cost of US$502,213.

In his letter to Sharma, Edghill attached a series of documents which detail his claims and carry dates between the period of December, 2018 and December, 2019.

“The contracting agency accepted the projects (construction of the overhead walkways) as substantively completed and took over the works in accordance with Clause 56.1 of the conditions of the contracts,” Edghill said.

He added that as it relates to the supply, installation and maintenance of the solar voltaic systems, the contracting agency accepted the project as substantially completed.

Maintenance

In the letter, Edghill further explained that in November, 2017, it was announced that the crossings and the elevators would be maintained and managed by the Demerara Harbour Bridge Corporation (DHBC).

As a result, he said the infrastructure was handed over to former General Manager of the DHBC Rawlston Adams. This allowed Adams to access the electrical rooms and the interconnection of the CCTV systems at each of the overpasses.

Additionally, the Peters Hall overpass was provided with electricity from the DHBC, according to Edghill and the DHBC and eGovernment agency, the National Data Management Authority (NDMA) installed equipment at the overpasses.

A few months after, Edghill noted that an agreement was signed by the DHBC with the then Public Infrastructure Ministry to manage and maintain the overpasses which included its cleaning on the condition that revenue would be recovered for these costs from advertising.

According to Edghill, the elevators arrived here in February, 2018 and installation commenced in June, 2018.

Several months after, they were commissioned with the period for maintenance beginning from November 1, 2018 for a period of one year.

Following this, Edghill said personnel received training on how to operate and maintain the elevators.

Edghill added that for close to a year after commissioning, the elevators were inoperable and remained closed.

During this period, there were incidents of vandalism and in all instances repairs were carried out by the Ministry. Edghill said that the DHBC failed to provide any footage of these incidents.

Technical difficulties

In August, 2019, the overpass at Peters Hall was commissioned and it was open for use by the public.

Edghill said in his letter that subsequently a number of technical difficulties emerged including door lock not opening or closing, elevator malfunctioning while persons were inside among others.

As a result, Edghill said that RBP Lifts, the company which installed the elevators and the local representative who was responsible for quarterly maintenance were summoned on numerous occasions.

The local representative was unable to rectify some of the issues.

During September, 2019, an incident occurred where persons were stuck in the elevator. The Ministry learnt of this via social media.

Edghill said the issue was looked into and repairs were done. As such, the elevators were back in operation.

“No further communication was received from DHBC as the said agency’s personnel had been trained and had been introduced to the local elevator representative, and there was no indication that the elevators were not performing or working as per manufacturer’s specifications. There was also no notice from DHBC that the elevators were as a consequence closed,” Edghill noted in his letter.

He added that the DHBC had reported that after the issue was rectified, it recurred.

“The elevators would work excellently for about 20 minutes then start exhibiting the same problems of not locking, or opening, errors indicating control board faults, screen displays malfunctioning,” Edghill said.

He said on several occasions efforts were made by the local representative to fix the issue but they were fruitless.

As a consequence, in February, last year, he said the elevators at Peters Hall stopped working since the issues were not rectified and it was unsafe for persons to use them.

Presently, Edghill said the elevators have various defects.