Minister of Public Works, Juan Edghill last Friday announced that major upgrades to the Kingston Goods Wharf and Port Kaituma, Kumaka and Morawhanna stellings are slated for completion during the third quarter of 2024.
He made this disclosure during a year-end press briefing held at the Ministry’s office in Wight’s Lane, Kingston, Georgetown.
“We have four major multimillion projects ongoing in terms of the development of our stellings. The Kingston Goods Wharf is 35% completed, the Port Kaituma stelling is 77% completed, the Kumaka stelling is 18% completed and the Morawhanna stelling is 34% completed. All of these stellings should be completed no later than the third quarter of 2024,” Edghill said.