The Ministry of Public Works today said that a four-point plan has been produced for travel in the Pirara area, Region Nine which has been beset by flooding.
The plan follows:
1. Temporary Timber Deck: Half of the new bridge’s completed piers and abutments will be outfitted with a temporary timber deck for light to medium-weight vehicles. The contractor is securing appropriate timber and expects to begin this week.
2. Phased Construction: Once the temporary deck is complete, the contractor will build the second half of the bridge using steel beams and a concrete deck. Traffic will then shift to the finished section, allowing work on the remaining half.
3. Boat Assistance (Temporary): Until the wooden deck is operational, the Lethem Mayor and Town Council, in collaboration with the Regional Democratic Council (RDC), will continue to assist travelers crossing the affected area by boat.
4. Repairs on Other Affected Sections: Efforts are underway to address other flood-damaged sections of the road. Drivers are urged to exercise caution, especially in areas with high water levels.