President expresses satisfaction with ongoing works at Marriott’s Timehri hotel

Chief Executive Officer (CEO) of Cardinal Investments Inc, Roy Bassoo

President Irfaan Ali, yesterday inspected ongoing works at the Courtyard by Marriott Hotels International, Timehri where he expressed satisfaction with the progress of works completed.

Completion of this hotel has been severely delayed. The sod was turned on July 2nd, 2021 and the hotel was originally supposed to be completed in the early part of 2023.

The six-storey edifice is being constructed on 2.5 acres of land leased from government and features 150 rooms, including five executive suites. Chief Executive Officer (CEO) Roy Bassoo of Cardinal Investments Inc., the company executing the project, disclosed that works are expected to be completed by March 2025. The new completion date allows for the execution of additional works.